14 · The Sampling Cycle
Weeks 14–16 · 60 hours across three weeks
Objective
Run a professional sampling process: know what each sample round is for, how to evaluate a sample rigorously, and how to write comments a factory can act on without ambiguity.
Why it matters commercially
Sampling is where your shoe becomes real, and where most of your remaining risk lives. Each round costs weeks and money. Brands that sample well need two rounds; brands that sample badly need five and run out of both.
Core concepts
The rounds and what each one is for
| Round | Also called | Purpose | What you’re judging |
|---|---|---|---|
| Last confirmation | Approve the last before anything is built on it | Shape, volume, profile | |
| Pull-over | Fitting upper | Upper pulled over the last, no sole | Pattern accuracy, panel proportions, how lines sit in 3D |
| Proto / P sample | 1st sample, development sample | Prove the construction works | Construction, fit, proportion. Materials and colours are often wrong on purpose — don’t panic |
| 2nd / 3rd proto | Correct the proto’s faults | Whatever you commented on | |
| Salesman sample / SMS | Sales sample | Selling and photography | Correct materials and colours, presentable finish |
| Fit / wear-test sample | Real-world validation | Comfort over hours, hot spots, durability | |
| Size-run sample | Grading sample | Validate grading | Fit at the extremes of your size run |
| Confirmation / PP sample | Pre-production, golden sample | The contractual reference | Everything. This is what bulk is judged against |
The golden sample. When you approve the confirmation sample, you sign and date it, the factory keeps one signed pair and you keep one signed pair. Bulk production is judged against it. If a dispute arises, the golden sample is the evidence. Never skip this, never approve it by photograph.
Your Week 13–19 plan runs: proto (W13–16) → corrected sample with correct materials (W16–19) → confirmation approval (W19), with a size-run sample requested alongside round two. If round two isn’t right, take a third and slip the schedule. Shipping a bad shoe is more expensive than shipping a late one.
How to evaluate a sample
Do this systematically, over two sessions, not in the excited first ten minutes.
Session 1 — against the spec (2h). With tech pack open:
- Check every BOM line against what’s physically there
- Measure everything you dimensioned: topline heights, eyelet spacing, logo position, panel breaks, stack heights
- Check panel shapes against your drawings
- Check colour against your lab dips, in daylight
- Check stitching: seam type, rows, SPI, thread colour, straightness, backtacks
- Check the bite line for evenness all the way round
- Check the bond: press and flex the toe and heel, look for gaps or glue squeeze-out
- Weigh the pair
- Check both shoes against each other — asymmetry between left and right is a common and revealing fault
Session 2 — on foot (4h+). Wear them. Then wear them for a full day. Then have two other people in your sample size wear them.
- Getting on and off — long heel girth
- Heel hold walking and on stairs — short heel girth, counter
- Toe room, both length and height
- Where does it crease, and does the crease hurt?
- Pressure points: eyestay edges, collar, tongue edges, backstay seam
- Sole flex point — does it flex where your foot flexes?
- Any noise, any slipping, any hot spots after 3 hours
Writing sample comments
The professional format: a comment sheet — one row per issue, with a photograph, the spec reference, what’s wrong, and the required correction. Not a paragraph of prose. Not a WhatsApp voice note.
| # | Photo | Location | Spec ref | Issue | Required correction | Priority |
|---|---|---|---|---|---|---|
| 1 | img_01 | Lateral quarter | TP V02 p.7 | Panel break sits 6mm too far forward | Move panel break 6mm toward heel, per drawing | Must fix |
| 2 | img_04 | Collar | TP V02 p.11 | Foam too soft, collar collapses | Increase collar foam density; send two options | Must fix |
| 3 | img_09 | Topline | — | Topline height 58mm, spec 54mm | Reduce to 54mm ±2mm | Must fix |
| 4 | img_12 | Backstay | TP V02 p.9 | Stitch 6 SPI, spec 8 SPI | Correct to 8 SPI | Should fix |
Use Must fix / Should fix / Note only. This prioritisation is a gift to the factory and dramatically improves what comes back.
Number your photographs and reference them. Annotate them with arrows. Send one PDF, not fourteen images.
Managing the relationship through sampling
- Reply within 48 hours, always. Your responsiveness sets theirs.
- Approve loudly what’s right, not just what’s wrong. Factories rarely hear this and it changes how they treat you.
- When you change something, note that it’s a change and accept it may affect price and date.
- Ask “what would you do?” on anything you’re unsure about. They’ve made a hundred thousand shoes.
Do this
Week 14 — while the proto is in production (20h)
- Build your sample evaluation checklist as a reusable document (4h).
- Build your comment sheet template (2h).
- Wear-test protocol: write the exact protocol you’ll use, including who tests, for how long, and what they record (3h).
- Get ahead: start Module 15 reading on QC and testing (6h).
- Order the size-run/grading samples for round two (1h).
- Outreach: material suppliers, lab dip requests, packaging suppliers (4h).
Weeks 15–16 — proto arrives and round two ordered (40h)
- Full spec evaluation, Session 1 (3h).
- Wear test, Session 2, across several days (6h across the fortnight).
- Third-party eyes: three people handle and wear the sample and give you unfiltered reactions (3h).
- Write the comment sheet (6h). Photograph properly — daylight, plain background, consistent angles.
- Video call with the factory to walk through the comment sheet live (2h). Do not rely on email alone for a first sample review.
- Issue tech pack V03 with all corrections incorporated, and order round two with correct materials and colours (6h).
- Approve lab dips physically (2h).
- Start Module 15 in earnest (12h).
Deliverable. A reusable evaluation checklist and comment sheet template; a completed, photographed comment sheet for the proto; documented wear-test results from at least three people; tech pack V03; a confirmed round-two order including size-run samples; physically approved lab dips.
Self-check
- What is a pull-over sample for, and why would you ask for one?
- Why are materials often wrong on a proto, and why is that fine?
- What is a golden sample and what makes it contractually important?
- Give the columns of a good comment sheet.
- Name six things to check on foot that you cannot check on a table.
Traps
Approving from photographs. Never. Not the sample, not the lab dips, not the packaging.
Emotional first reactions. Your first sample will disappoint you. That is universal and expected. Wait 24 hours before writing comments.
Vague comments. “The toe looks off” produces another wrong sample. “Reduce toe box height by 4mm at the centre, per revised drawing p.7” produces a right one.
Changing the design during sampling. Correcting faults is sampling. Redesigning is starting over. Know which one you’re doing and be honest with yourself about it.
Not wear-testing. A shoe that photographs beautifully and hurts after two hours will generate returns and never a second order.